Hello! I've saw in the ATEasy Examples package, that some programs include the following structure of the tests/tasks: under the Tests submodule -> Task1 -> Task1.1 -> Test1.1.1 etc. But I couldn't build that! All I can is the following: Tests -> Task1 -> Test1.1 and so on, but without the Task1.1 interleaved.
Is there a special way to build another Task within the hierarchy? Please help me.

Solution Available
Dale J.
La Verne, CA

Oct 12, 2011
22 Posts

1  |  0  

Re: How can I create a new task within a task?

Hi John,
You can set the number of Task levels, and whether Tasks and Tests can reside at the same level, by selecting the "Tools:Option:Tests/Procedures" tab from the menu.  The default Tasks Level is limited to one when you install ATEasy.  Once the levels are changed, you can insert Tasks/Tests using the Insert At/After/Below menu or tool-bar icon.

Regards,
Dale

John K.
Bacau,

Oct 12, 2011
55 Posts

0  |  0  

Re: How can I create a new task within a task?

Thank you very much, Dale! Have a nice day.

Best regards,
John K.



Please Note
You need to have a M@GIC account to participate in the Forums.
Not yet registered on our website? Click here to register today!

All content, information and opinions presented on the Marvin Test Solutions User Forums are those of the authors of the posts and messages and not Marvin Test Solutions'. All attachments and files are downloaded at your own risk. [Read More]